Putting in the Foundation
Click on the pictures below to see a larger version with explanation (about 45K each)

The outline of the house chalked on the ground - Sept 4, 1998
|

Digging the trench in preparation for pouring the footer - Sept 8, 1998
|

Pouring the footer (with the trailer and shed in the background) - Sept 11, 1998
|

Starting the stem wall - Sept 14, 1998
|

Finishing the stem wall - Sept 15, 1998
|

Pouring the grout in the stem wall - Sept 16, 1998
|

Subslab plumbing installed - Sept 25, 1998
|

Fill compacted for slab - Sept 28, 1998
|

Pouring the subslab - Sept 29, 1998
|

Laying the radiant heat tubing - Oct 8, 1998
|

The radiant heat tubing installed - Oct 12, 1998
|

Pouring the upper slab - Oct 20, 1998
|

Scouring the upper slab - Oct 20, 1998
|