Interior Walls and Doors

Click on the pictures below to see a larger version with explanation (about 45K each)


Interior doors stained -
May 2, 1999


Placing insulation in the attic -
May 11, 1999
 

 
Insulation in the walls -
May 11, 1999


Machinery for putting drywall on the ceiling - May 12, 1999


Drywall being installed -
May 13, 1999


Drywall complete -
May 17, 1999


Taping the walls -
May 28, 1999


Installing plaster corners -
May 28, 1999


Laying tile on the bedroom ceiling - May 28, 1999


Ceiling complete -
June 1, 1999


Baseboard tile -
June 2, 1999


Bathtub tile - July 7, 1999


Bathroom deco tile -
July 7, 1999


Bedroom deco tile -
July 16, 1999


Begin plastering -
July 26, 1999


Plastering the bathroom ceiling -
August 5, 1999


Bathroom plastered -
August 5, 1999


Bedroom grouted -
August 6, 1999


Tiling the floor -
August 19, 1999


Floor completely tiled -
August 30, 1999


Doors installed -
September 22, 1999


Cabinets