Pictures of Construction

(Click on the images to see more pictures)


Putting in the foundation
(Sep 4, 1998 - Oct 20, 1998)


Building the block wall
(Oct 26, 1998 - Nov 13, 1998)


Putting on the roof
(Nov 11, 1998 - Dec 29, 1998)


Framing the walls
(Nov 23, 1998 - Dec 18, 1998)


Air venting and electrical installation
(Jan 5, 1999 - Apr 18, 1999)

 
Interior floors and walls
(May 1, 1999 - Sep 22, 1999)


Cabinets and plumbing
(Jun 18, 1999 - Feb 25, 2000)


Landscaping
(Jun 15, 1999 - Oct 30, 1999)


The Pond
(Jan 4, 2000 - Feb 18, 2000)